Power outage in 2 areas
Electricity remains off in Soshanguve Block R after the planned interruption window ended at 16:00. Delayed cable transfers at Soshanguve W-Substation have postponed the planned switchback until midnight. Electricity is also off in Soshanguve KK.

Key facts
- Repair time
- 20 Oct 16:00, from the official notice.
Timeline
Electricity is off across Soshanguve KK.
A notice says the Soshanguve W substation switchback is delayed until midnight on 20 October while cable-transfer work continues.
A utility update says delayed cable transfers at Soshanguve W-Substation have postponed the planned power switchback affecting Soshanguve Block R until midnight.
Electricity remains off in Soshanguve Block R after the planned interruption window ended.